Plot Allotment Notification
Nov 06, 2018
Online Application for allotment of Industrial Plots at TMTP has to be submitted to KUM by visiting https://kum.karnataka.gov.in.
| SL.No. | NAME OF THE COMMITTEE | ACTION BY THE COMMITTEE |
|---|---|---|
| 1 | State Level Single Window Clearance Committee (SLSWCC) | To Examine and consider the proposals up to Rs.500 Crores. |
| 2 | State High Level Clearance Committee (SHLCC) | To Examine and consider the proposal above Rs.500 Crores. |
On approval of project by the competent committee the Applicant needs to submit the following documents to KIADB along with an initial deposit of 30% of the land.
| SL. NO. | ON CLEARANCE OF THE PROJECT BY SLSWCC | TIME FRAME |
|---|---|---|
| 1 | Along with the application with relevant documents 30% initial deposit on Tentative land cost to be paid to KIADB | 30 days from date of communication |
| 2 | Balance 70% (Land cost) | 90 days from the date of allotment letter. |
| 3 | Obtaining Possession Certificate. | 1 month after confirmation of allotment |
| 4 | Execution of Lease cum sale deed | Within one month from the date of Possession Certificate |
| 5 | Sanction of building plan | Within 6 months from date of execution of Lease cum sale deed |
| 6 | Completion of construction of the Industrial building, installation of Machinery and commencement of production | Within 36/60 months from the date of possession. |
To Apply for TMTP
Tumakuru Machine Tool Park (TMTP), is a Special Purpose Vehicle (SPV) of Government of India and Government of Karnataka.